Making the most of my "Dash"

Posts tagged ‘Concrete’

We’ve got concrete!

Today was the big day for getting the concrete slabs poured!  Yesterday they finished the prep work, and we had concrete being poured by 9:30 this morning!  At one point we even had two concrete trucks on both ends of the little garage.  That was pretty cool.  They’re still out there doing finishing work on it, but it looks great.  They should start framing in a few days.  We are happy campers!!

Beast's garage... ready for concrete!

Little garage... all ready too!

Pouring into the back of the Beast's garage from the side, because the gas line is in the way

Pouring from the front now, under Mister's watchful eye.

Working around the suspended gas line was a PITA, I'm sure. But they did a great job!

They ran concrete along the side of the walls, and then filled in the middle.

Working on the right side now...

It's coming along nicely!

Mister busy supervising...

A double pour!

Getting it done!

Doing finish work on the Beast's garage, while the others were still pouring the little garage's slab

Purty!

Another Purty!

A view from the other side...

Advertisements

Another Garage Update!

Mister is getting excited.  There is finally some progress being made!  This week they removed the eave from the existing garage.  They also dug the trench and placed the forms for the smaller garage’s footings, and set the forms for the stem-walls in the Beast’s garage.  This morning we woke up to a concrete truck in our backyard.  Awesome!!

Next week they will prep the ground in the small garage for the slab to be poured.  The Beast’s garage is pretty much ready, as they have already leveled the ground, added dirt, and then tamped it down.  When they end up pouring the slab for that garage, they will end up removing all the wood they’ve placed around the gas line to protect it.  We were told they will end up placing a board above the line to suspend it while they do the pour.  We can tell it has really been a real PITA having to work around it.  The utility company *only* wanted $22.50/foot to temporarily move the line.  Obviously we didn’t pay that outrageous amount, and so the workers have to tread carefully around it. They are enjoying that tremendously…

Next update should have slabs poured. Until then, here are some pictures…

No more eave...

Small Garage Footings

Protecting the Gas line.

Prepping the Beast's toilet for the concrete pour

Good Morning, Taz Concrete!!

All done. Time to cure...

They removed the inside forms during the afternoon to smooth out the footings. Purty.

The stem-walls in the Beast's garage

Top view of the stem-walls

Tag Cloud

%d bloggers like this: